The safety operation of the laboratory gas crushing machine should pay attention to the safety opera

The airflow crusher of the inert gas protection laboratory recycles air cooling. Because the entire system is a closed circular circulation system, there are multiple motion components inside the device, which will generate a certain temperature in high -speed exercise, and temperature is critical to process safety in processing. Therefore, the device is equipped with a radiator cooler on the pipeline, which can effectively reduce the safety hazards caused by the equipment for a long time or under the high temperature environment.

Powder equipment display diagram

The safety operation of the laboratory air flow crusher should pay attention to the following points:

1. Before the laboratory air flow crusher starts, you should check whether the various components of the equipment should be complete and ensure that it should ensure that The part is not loose

Move, you can start the device after confirmation.

2. The electric box and the motor must be grounded.

3. When the device is started, it is forbidden to touch any rotating parts, and the hand is prohibited from putting the hand in the outlet to prevent

accidents or personal injury.

4. It is forbidden to do equipment maintenance and maintenance work under the condition of electricity and gas.

The order of booting:

1. Open the cooling water and start the air compressor. After the air load runs for 2-3 minutes, it is in the normal runtime

state.

2. Start the refrigerator (connected to the cooling water of the cooling water and the air compressor).

3. The air compressor and freezer dryer work normally. After the air pressure reaches 0.7 MPA -1MP A, start the master

, adjust to the required speed, and then start the fan. Adjust to the required speed, and then start the fan.

4. Before opening the laboratory airflow crusher main trachea, adjust the motor bearing gas sealing pressure 0.03MPa-0.05MPa

. After the above content is checked, the feeding and crushing will be added.

5. The pulse voltage pressure of the dust collector is adjusted to about 0.4MPa.

6. Adjust the material rough or thin according to the need, adjust the speed of the host hierarchical wheel speed: low and thick, high fine.

7. In the process of making the material after the material is crushed, some materials are tapped by the leather hammer to convey the pipeline, the whirlwind

outer wall of the dust collector, so as not to close the dip and cause the pipeline to cause the pipeline Covering and affecting normal discharge.

The order of the shutdown (after stopping the feeding):

1. Turn off the main tracheal valve, wait for the compressor to discreate, turn off the air pressure machine, turn off the freezer dryer, and then check it [123 ]

The infiltration fan, when the speed of the fans drops to less than half, turn off the inverter, turn off the dust collector, and turn off the material valve.

2. When the temperature of the air compressor is less than 60 \u0026 deg; C, turn off the cooling water.

3. Regarding pulse dust removal: When the airflow crusher of the laboratory is stopped every day, let the pulse instrument work 5--1In 0 minutes,

Rinse the powder adsorbed on the filter bag and keep it smoothly.

As a world country, China has played a positive role in maintaining the stable development of world peace and regional, and has assumed the responsibility and obligation of the great power.As a large -scale industrial powder equipment manufacturing enterprise developed in China's economic wave, Youmingke Fan Machinery will also assume corporate social responsibility, and continue to work with more companies to add bricks to my country's strong army and the road of strong nations.